The Wayanad Tunnel Project has entered a major construction phase, with significant developments reported from both Marippuzha (Kozhikode side) and Meppadi (Wayanad side).
The biggest highlight:
The first rock blasting at Marippuzha was successfully carried out on March 6, 2026, marking the official beginning of tunnel excavation activities.
Overall Waynad Tunnel Updates April 2026
- Project has moved into active construction stage
- Tunnel excavation officially initiated (Marippuzha side)
- Meppadi side progressing with large-scale groundwork
- Simultaneous development at both tunnel portals
Marippuzha Side (Kozhikode) – Latest Tunnel Updates
March 6, 2026 – First blasting at Marippuzha
- Marks the official start of tunnel excavation
- Entry into the most critical construction phase
- Confirms that groundwork and approvals are completed
Current Activities:
- Rock excavation and debris clearing
- Tunnel portal shaping and reinforcement
- Continuous drilling and controlled blasting
- Deployment of heavy machinery at tunnel entrance
Meppadi Side (Wayanad) – Latest Tunnel Updates April 2026
The Meppadi side is showing strong and visible progress in terrain preparation and infrastructure setup.
Key Developments:
- Massive hill cutting and slope leveling
- Creation of terraced construction zones
- Development of wide access roads
- Installation of batching plants and machinery units
- Retaining walls for safety and slope stability
What This Means:
- Site is being prepared for tunnel portal excavation
- Indicates fast-tracked groundwork progress
- Ready to transition into blasting and excavation phase soon
Marippuzha Entry vs. Meppadi Entry
| Feature | Marippuzha Side (Kozhikode) | Meppadi Side (Wayanad) |
| Current Stage | Primary Tunnel Boring & Blasting | Portal Stabilization & Site Prep |
| Major Activity | Controlled Rock Blasting (Phase 2) | Soil Excavation & Reinforcement |
| Key Landmark | Swargamkunnu Entry Point | Meenakshi Hills (Kalladi) |
| Equipment | Hydraulic Boomers & Crushers | Piling Rigs & Shotcrete Machines |
Wayanad Tunnel Project - Latest Construction Images
The latest Wayanad Tunnel updates april 2026 bring great relief to residents, as the sight of heavy excavators and drilling rigs at Meenakshi Estate in Meppadi confirms steady progress. The project is moving forward from both sides, following a pincer approach designed to meet in the middle of the mountain by 2029–2030.
Images credits @Vishnu_km