Wayanad Tunnel Latest Updates – June 2026

The Aanakkampoyil–Kalladi–Meppadi Tunnel Road Project, popularly known as the Wayanad Tunnel Project, recorded significant progress during June 2026. The Wayanad Tunnel Updates June 2026 show that one of the most notable developments is the introduction of night-shift operations, allowing excavation work to continue around the clock and helping speed up the construction of Kerala’s longest road tunnel.

The project, which aims to provide an alternative route connecting Kozhikode and Wayanad while reducing travel time through the Thamarassery Ghat section, is steadily advancing despite the challenging geological conditions encountered in the initial stages of tunneling.

Overall Wayanad Tunnel Updates June 2026

  • Tunnel excavation progressing on both tunnel tubes
  • Right-side tunnel reached approximately 30 metres (Marippuzha Side)
  • Left-side tunnel reached approximately 10 metres (Marippuzha Side)
  • Night-shift operations introduced
  • Excavation expected to accelerate after the first 50 metres
  • Service bridge over Iruvanjippuzha nearing completion

Marippuzha Side (Kozhikode) – Latest Tunnel Updates

wayanad tunnel project
  • The right-side tunnel, where excavation commenced first from the Marippuzha side, has now reached approximately 30 metres, while the left-side tunnel, which began later, has progressed to around 10 metres.
  • Tunnel construction activities are now being carried out in both day and night shifts, allowing excavation work to continue around the clock and improving overall project progress.
  • The service bridge across the Iruvanjippuzha River, providing access to the tunnel entrance area, is now almost complete, significantly enhancing site connectivity for workers, machinery, and construction materials.

Meppadi Side (Wayanad) – Latest Tunnel Updates June 2026

Meppadi tunnel project updates
  • Preparatory works are progressing steadily at the Kalladi–Meppadi tunnel entrance, with site development, slope stabilization, and access infrastructure works continuing to support the commencement of tunneling activities from the Wayanad side.
  • Project authorities have indicated that the first controlled blast at the Meppadi tunnel portal is expected to take place shortly, marking the beginning of excavation works from the Wayanad side of the tunnel project.
  • Construction and improvement of approach roads around the tunnel entrance area are advancing, ensuring smooth movement of workers, machinery, and construction materials to the project site.
wayanad tunnel updates june 2026

Night Shift Operations Introduced

A major milestone in June 2026 is the commencement of night-shift operations at the tunnel construction site. Work is now being carried out in two shifts, allowing excavation activities to continue both day and night.

This move is expected to improve project efficiency and accelerate the construction timeline of the Anakkampoyil–Kalladi–Meppadi Tunnel Road Project.

Service Bridge Near Tunnel Entrance Almost Complete

Another important development is the near completion of the service bridge across the Iruvanjippuzha River leading to the tunnel entrance area.

With continuous day-and-night excavation now underway and supporting infrastructure works progressing simultaneously, the Wayanad Tunnel Project entered a more active construction phase during June 2026.

The coming months will be crucial as tunneling advances beyond the initial challenging section and major approach road and bridge works gain momentum. If current progress continues, the project could witness substantially faster excavation rates and visible construction milestones in the second half of 2026.

Stay tuned for more Wayanad Tunnel Project updates, tunnel construction progress reports, excavation milestones, and infrastructure developments as work continues on Kerala’s landmark Anakkampoyil–Kalladi–Meppadi Tunnel Road Project.

wayanad tunnel project
Wayanad Tunnel Latest Updates 2026
Kozhikode Wayanad tunnel road map
Wayanad Tunnel Road Map Explained
Wayanad Tunnel opening
When Will the Wayanad Tunnel open ?

Explore Wayanad – Kerala’s Most Beautiful Hill District

With easier access through the new tunnel, traveling to Wayanad will become much faster. Discover waterfalls, wildlife, trekking spots, and scenic viewpoints in Wayanad.